UC Davis Health Construction Update - March 2021

UC Davis Health Parking Structure 4 Construction Update - March 2021

UC Davis Health Parking Structure 4 Construction Rendering
UC Davis Health Parking Structure 4 Construction Rendering

Current Construction Activities

  • Precast Erection commenced 2/3/2021. Erection will continue through mid-April.
  • Continued work on new utility installation including Fire Water and Domestic Water at West/South/East sides of structure.
  • Curb and Gutter Installation along new X-Street Alignment.

Upcoming Activities

  • Topping slab and mechanical, electrical and plumbing work to commence week of March 15, 2021. Topping slab work will continue through April.
  • Underground utilities within the structure footprint will start in March 2021.
  • Traffic control signal underground work starting second week of March.

 

UC Davis Health Eye Center Construction Update 

UC Davis Health Eye Center Construction Rendering
UC Davis Health Eye Center Construction Rendering

Current Construction Activities

  • Interior utilities conduit, ductwork, and plumping piping continuing
  • Metal stud framing layout starting
  • Exterior Curtain walls installation continue

Upcoming Activities

  • Pour stair treads
  • Interior metal stud framing work to commence
  • Interior utilities work begins
  • Building enclosure to dry-in
  • Roofing System installation