UC Davis Health Construction Update - March 2021
UC Davis Health Parking Structure 4 Construction Update - March 2021
Current Construction Activities
- Precast Erection commenced 2/3/2021. Erection will continue through mid-April.
- Continued work on new utility installation including Fire Water and Domestic Water at West/South/East sides of structure.
- Curb and Gutter Installation along new X-Street Alignment.
Upcoming Activities
- Topping slab and mechanical, electrical and plumbing work to commence week of March 15, 2021. Topping slab work will continue through April.
- Underground utilities within the structure footprint will start in March 2021.
- Traffic control signal underground work starting second week of March.
UC Davis Health Eye Center Construction Update
Current Construction Activities
- Interior utilities conduit, ductwork, and plumping piping continuing
- Metal stud framing layout starting
- Exterior Curtain walls installation continue
Upcoming Activities
- Pour stair treads
- Interior metal stud framing work to commence
- Interior utilities work begins
- Building enclosure to dry-in
- Roofing System installation