Health

UC Davis Health Construction Update - March 2021

UC Davis Health Parking Structure 4 Construction Update - March 2021 Current Construction Activities
  • Precast Erection commenced 2/3/2021. Erection will continue through mid-April.
  • Continued work on new utility installation including Fire Water and Domestic Water at West/South/East sides of structure.
  • Curb and Gutter Installation along new X-Street Alignment.
Upcoming Activities
  • Topping slab and mechanical, electrical and plumbing work to commence week of March 15, 2021.

The UC Davis Health Community Advisory Board is recruiting new members!

Interested in serving on a volunteer board that advises health system leaders on issues of interest to the broader community?

The UC Davis Health Community Advisory Board (CAB) is recruiting new members! A representative group of volunteer members who live and work in the Sacramento region, the CAB advises health system leaders on issues of interest to the broader community with a special focus on access to high-quality health care.