UC Davis Health Parking Structure 4 Construction Update - March 2021
Current Construction Activities
- Precast Erection commenced 2/3/2021. Erection will continue through mid-April.
- Continued work on new utility installation including Fire Water and Domestic Water at West/South/East sides of structure.
- Curb and Gutter Installation along new X-Street Alignment.
Upcoming Activities
- Topping slab and mechanical, electrical and plumbing work to commence week of March 15, 2021.